Activities schedule

PROJECT IMPLEMENTATION PLAN (TIME SCHEDULE)

ACTIVITIES
jun
2015
jul
2015
aug
2015
sept
2015
oct
2015
nov
2015
dec
2015
jan
2016
feb
2016
mar
2016
apr
2016
Activity 1: Project Management. x x x x x x x x x x x
Activity 2: Assignment of public procurement procedure. x x x x х
Activity 3: Inspection of funds and preparation for their cataloguing with specialized software. х х х х х
Activity 4: Maintenance on funds of manuscripts and old printed books. х х х х х
Activity 5: Establishment of two digital centres. Repairs. х х х
Activity 6: Delivery of hardware and software for the two digital centres. х х
Activity 7: Training digital centres employees to work with specialized software. х
Activity 8: Selective digitization of special collections of manuscripts and printed books from the funds of the project participants and graphic processing of the digital copies. х х х
Activity 9: Organizing a general catalogue of rare and valuable manuscripts and old printed books. х х
Activity 10: Building a virtual library with links to partner sites. х х
Activity 11: Inclusion of representatives of the Roma population in promotion of project results. х х
Activity 12: Presentation of activities and opportunities for future use of project results. х
Activity 13: Audit. х

 